NWA ramps up work along Morant Bay section of highway project

February 23, 2021

The National Works Agency (NWA), says it will be ramping up activities on the Southern Coastal Highway Improvement Project significantly for the next three months.

According to the NWA, the heightened road construction works will be concentrated primarily in the town of Morant Bay, St. Thomas where major pipe-laying activities are set to commence alongside ongoing civil works.

National Works Agency (NWA) Communication and Customer Services Manager, Stephen Shaw, explained that pipe-laying will be restricted to night time hours within the town limits in a bid to minimise disruptions to the movement of vehicular and pedestrian traffic.

He pointed out however, that despite the contractor’s best efforts motorists should expect there to be some impact on traffic flow, from time to time, as the works are being carried out in a largely urban setting.

The aim he said, is to have the entire stretch of roadway between the Morant Bay Roundabout and Wharf Road paved at the end of the ninety-day period.

Various other types of civil works will also continue over the entire nine kilometer stretch from the Morant Bay Roundabout to Prospect in a bid to complete the $1-billion Jamaican dollar contract package within the stated contract period of 19 months.

To date, 75% of the works on a major retaining sea wall in the vicinity of Morant Villas have been completed with now only a 4.5-metre high component outstanding.

Though some aspects of the concrete drainage works have been put on hold to facilitate the laying of water pipelines, which commenced recently other concrete works such as the installation of sidewalks and kerb and gutter are continuing apace.